Stationary pump skills
Operators and relevant equipment management personnel should carefully read the operating instructions and master structural principles, operation and maintenance as well as pumping concrete operations.
The ground supporting the stationary pump should be flat and solid. The pump location should not only be convenient for the concrete mixing truck to enter and exit and feed to the hopper, it should also be accessible for the pumping distribution pipe in order to reduce pumping pressure loss. At the same time, it should be close to the pouring site and convenient for power supply and water supply.
In the process of concrete pumping, with the increment of pump pressure, pumping impact may force the pipe to move back and forth. This may result in pumping pressure loss, which can lead to damage of the pipe clamp and aprons as well as other issues.
After being connected, the concrete pump should be inspected in accordance with the operating instructions, and the machine should not be started until it meets the requirements.
When construction takes place in hot weather, it is advisable to cover the concrete conveying pipe with a wet straw bag, wet cover cloth and other materials to avoid direct sunlight and prevent the concrete from blocking the pipe.
Horizontal pipes of a certain length should be laid between the concrete pump and the vertical piping to ensure sufficient resistance to prevent the back flow of concrete.
When construction takes place in cold weather, concrete conveying pipes should be wrapped with insulation materials to prevent the concrete inside the pipe from freezing.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
What they are, how they work and why they are popular in many countries.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.